The new Boca del Cerro Bridge on the Tren Maya, Mexico

We share photos of the first steel truss segment assembly of central section of the bridge.

Using a cantilever advance carriage, anchorage on the lateral span of the bridge, the segment (approximate weight of 100 tons) was moved to the edge of the cantilever and then controlled lowered to its final position.

This construction procedure avoids any condition or dependence on the Usumacinta River crossing.

The new viaduct is located parallel to and very close to the impressive Boca del Cerro arch bridge, in service since 1950, and allows jumping the great span of the river Usumacinta -the largest in Mexico-, respecting its integration into a natural environment of extraordinary beauty and avoiding “competing” with the existing bridge, which must continue to maintain its preponderance in the landscape.

More information:

https://lnkd.in/d2SCwRTa

Once completed, the bridge will become the largest span of all of the Maya train.

IDEAM | A TYLin Company is collaborating with Mota-Engil México, and has carried out the conception, the detailed design and is providing technical assistance during execution. Recal is the Mexican steel workshop that is executing the steel structure and VSL International Ltd. supplies the cantilever advance carriages.

Video with assembly sequence:

https://lnkd.in/eUW9UBWD